Change Orders

Background​

Change Orders are formal modifications to existing contracts that document changes to the scope of work, contract value, and/or schedule. In Site Specs, Change Orders can be created for both owner contracts (revenue) and subcontractor contracts (costs). Change Orders are typically generated from approved Request for Quotes (RFQs) and are used to formalize changes to the project scope, budget, and timeline.

Subcontractor Change Orders​

Creating a Subcontractor Change Order​

To create a Subcontractor Change Order, navigate to the Change Management tab within your project and find the CMI you want to create a Change Order from. You can select all of the line items you wish to include in the subcontractor's change order. As you select line item's you will notice only the available options remain enabled (i.e. 'Subcontract CO', 'Owner COR', 'Send RFQ').

NOTE: Site Specs will not allow you to use line items in more than one Subcontractor CO, Owner COR, or Owner CO.

Select CMI for Change Order

Click on the "Subcontract CO" button to initiate the process.

Create Change Order Button

On the Subcontract Change Order creation form, you will notice the following fields.

Required Fields​

  • Title - A clear and descriptive name for the Change Order
  • Designated Reviewer - The person with authority to review and approve the Subcontract CO
  • Request Received From - The originator of the Change Order (often the subcontractor)
  • Status - Current status of the Change Order
  • Contract - The subcontract being modified
  • Vendor - The vendor/subcontractor receiving the change order

Optional Fields​

  • Schedule Impact - Number of days added to the subcontractors project schedule if change order is approved
  • Reference - Reference to any tools, documents, or materials associated with the change order
  • Change Reason - Reason for the change in scope, price and/or schedule
  • Due Date- Date the signed subcontract is due
  • Invoice Date - Date the change order was invoiced
  • Paid Date - Date the invoice for the change order was paid
  • Signed CO Received Date - The date the signed CO was returned to the Designated Reviewer
  • Description - Detailed description of the change including a default disclaimer
  • Attachments - Any relevant documents, drawings, RFIs, correspondences, etc

Once you saved your subcontractor change order, you can view the subcontractor change order details shown below.

General Tab​

Sub CO Details

From the General Tab users can 'View PDF' to view the actual change order PDF document.

Sub CO PDF

Payment Schedule​

The Payment Schedule tab shows the line items included in the change order.

Sub CO Payment Schedule

The Related items tab is where users can link any additional related items to the change order including, RFIs, Submittals, Documents, etc.

Sub CO Related Items

Approving Subcontractor Change Order​

Once the subcontractor change order status is changed to 'Approved' the values will be added to the subcontractor's current payment schedule and can be included in future pay applications.

Users can also add the change order to the 'Contracts' tab of the project where it will be linked to the Master Subcontract for that vendor. If your company has integrated the Adobe Sign API, Site Specs can also send the change order for digital signature. This is done by clicking the 'Send for signature' button in the subcontract change order detail view for 'Approved' change orders.

Owner Change Orders​

Owner change orders are generated by first creating CMIs, then generating an 'Owner Change Order Request' (COR), from which user's can then create an Owner Change Order.

To create an Owner Change Order, navigate to the Change Management tab within your project and find the CMI you want to create a Change Order from. You can select all of the line items you wish to include in the owner change order. As you select line item's you will notice only the available options remain enabled (i.e. 'Subcontract CO', 'Owner COR', 'Send RFQ'). In this example, we will create an Owner Change Order Request (COR).

NOTE: Site Specs will not allow you to use line items in more than one Subcontractor CO, Owner COR, or Owner CO.

Select CMI items for Owner COR

Creating an Owner Change Order Request​

To create an Owner Change Order Request (COR), after selecting the line items, click 'Owner COR' beside the search bar.

Create Owner COR

You will see the Owner COR creation form with the following fields.

Required Fields​

  • Title - A clear and descriptive name for the Change Order (refer to your company's standard operating procedures)
  • Status - Current status of the Change Order
  • Request Received From - The originator of the Change Order (often the subcontractor)

Optional Fields​

  • Schedule Impact - Number of days added to the project schedule if change order is approved
  • Reference - Reference to any tools, documents, or materials associated with the change order
  • Change Reason - Reason for the change in scope, price and/or schedule
  • Due Date- Date the signed COR is due
  • Invoice Date - Date the change order was invoiced
  • Paid Date - Date the invoice for the change order was paid
  • Signed CO Received Date - The date the signed CO was returned to the Designated Reviewer
  • Description - Detailed description of the change including a default disclaimer
  • Attachments - Any relevant documents, drawings, RFIs, correspondences, etc

Once you save your owner change order request, you will see the owner COR details view with the General, Payment Schedule, and Related Items tabs.

General Tab​

From the General Tab users can 'Create Owner CO' to create an owner change order (see below Creating an Owner Change Order).

Owner COR General Tab

Payment Schedule​

The Payment Schedule tab shows the line items included in the change order request.

Owner COR Payment Schedule Tab

The Related items tab is where users can link any additional related items to the change order including, RFIs, Submittals, Documents, etc.

Owner COR Related Items Tab

Creating an Owner Change Order​

Once one or many owner change order requests have been generated, users can then create owner change orders composed of one or many change order requests.

To do this, users can either navigate into a specific owner change order request (COR), OR they can

Owner Change Order from Owner Change Order Requests (COR)​

Click 'Create New Owner CO'

Owner COR General Tab

Owner Change Order from the Owner Change Order Log​

Click 'Create New Owner CO'

Owner CO Log

Once, user click 'Create New Owner CO', they then complete the owner change order creation form shown below.

Create Owner CO

Required Fields​

  • Title - A clear and descriptive name for the change order (refer to your company's standard operating procedures)
  • Status - Current status of the change order
  • Designated Reviewer - The final approver of the owner change order (often the project manager)

Optional Fields​

  • Revision Number - Number of the revision
  • Schedule Impact - Number of days added to the project schedule if change order is approved
  • Due Date- Date the signed change order is due
  • Invoice Date - Date the change order was invoiced
  • Paid Date - Date the invoice for the change order was paid
  • Signed CO Received Date - The date the signed CO was returned to the Designated Reviewer
  • Select Owner COR - Select all owner CORs to include in this owner change order
  • Description - Detailed description of the change including a default disclaimer
  • Attachments - Any relevant documents, drawings, RFIs, correspondences, etc

Once you save your owner change order, you will see the owner CO details view with the General, Payment Schedule, and Related Items tabs.

General Tab​

From the General Tab users can 'View PDF' to view the owner change order document.

Owner CO General Tab

Payment Schedule​

The Payment Schedule tab shows the line items included in the change order request. User's can edit and add line items as needed.

Owner CO Payment Schedule Tab

The Related items tab is where users can link any additional related items to the change order including, RFIs, Submittals, Documents, etc.

Owner CO Related Items Tab

To Update the status of the owner change order go to the General tab of the change order, click 'Edit' and change the status. Once the status is Approved, the value of the change order will be added to the appropriate lines in the Revenues Payment Schedule.

Managing Change Orders​

Once created, Change Orders can be managed through the Change Order log view.

Change Order Log

Users can:

  • Filter and search Change Orders
  • Manage columns to customize their view
  • Track Change Order status and progress
  • View related CMIs, RFQs, and documents
  • Export Change Order data

Change Order Workflow​

  1. Draft - Initial creation of the Change Order
  2. Pending Approval - Change Order is awaiting approval
  3. Approved - Change Order has been approved
  4. Executed - Change Order has been signed by all parties
  5. Rejected - Change Order has been rejected
  6. Closed - Change Order process is complete

Change Order Types​

Owner Change Orders​

  • Document changes to the owner contract
  • Impact project revenue
  • Require owner approval
  • Update owner payment schedule

Subcontractor Change Orders​

  • Document changes to subcontractor agreements
  • Impact project costs
  • Require subcontractor approval
  • Update subcontractor payment schedule

Things to Consider​

  • Ensure all changes are properly documented and approved
  • Include all relevant drawings, specifications, and documents
  • Track the impact on both schedule and budget
  • Maintain clear communication with all stakeholders
  • Use the comments section to document important discussions
  • Link related documents, CMIs, and RFQs for easy reference
  • Consider using templates for common types of changes
  • Keep detailed records of all approvals and signatures

Issues or Questions?​